FREE TOOL

Shed base calculator

Enter your shed size and ground. We compare every common base side by side: materials, quantities, cost, time and how much height each one adds for the planning rules.

Your shed

Units
How level is the ground?
Soil
Who is building it?

Planning height check

Within 2 m of a boundary?

In England, a garden building within 2 m of a boundary must stay under 2.5 m in total height to avoid planning permission, and the base counts. Planning rules explained.

Your answers stay in this browser.

Base options compared

DIY materials are priced from UK merchants, checked 28 November 2026, including VAT and before delivery. Fitted costs are ranges from published UK trade cost guides. Quantities include a 10% allowance. Bulk bags round up, so on a small base a few bagged aggregates from a merchant can cost less. Check ground conditions on site; heavy buildings and poor ground need a professional.

Price the whole shed in the builder

Choose a base that suits the shed

Start with the ground, not the price. A base needs to stay level, carry the building without rocking and keep the floor clear of standing water. For a heavy log cabin, workshop or garden office, follow the maker's foundation specification. For an ordinary timber shed, compare five practical approaches and the height each one adds.

Choose concrete for a permanent, solid platform. Choose paving slabs when you want a hard surface without mixing a full slab. A gravel-filled plastic grid is quick and drains well, but depends on good preparation. Bearers on pads suit a timber-floor shed where you can make several supports level. Adjustable pads help with fine-tuning, but their maker must confirm the load capacity.

Before marking out, check how shed foundations work and where to put a shed. Leave room to inspect and treat the back. Do not use a fence as structural support.

The five options in plain English

Concrete slab

A 100 mm slab over 75 mm of compacted MOT Type 1 gives a strong, continuous base for most garden sheds. The calculator adds a damp-proof membrane, shuttering and a general-purpose mix (1 part cement to 2 parts sand and 4 parts coarse aggregate, or all-in ballast). You need to level and compact the sub-base carefully, then wait up to 28 days before building on the slab. Concrete is the sensible choice for a heavy building, but it is the hardest option to remove or alter.

Paving slabs

The paving option uses 600 x 600 x 38 mm utility slabs over 100 mm of sub-base. Marshalls shows a 25 mm full mortar bed, while coarse sharp sand can be used on firm ground. A mortar bed gives better support for a shed base than isolated blobs. The finished surface adds less height than a slab, but every slab must be fully supported and the whole area must remain level.

Plastic grid

The grid option uses 500 x 500 x 40 mm panels filled with 10 to 30 mm angular gravel. A weed membrane sits below the prepared area. This permeable base is quick to install, but the grid is not a substitute for removing soft ground and compacting a sub-base. The manufacturer states a maximum slope tolerance of 25%, or 15 degrees. On a steeper site, get advice.

Timber frame on pads

This method places treated 100 x 50 mm bearers on supports at about 600 mm centres. The supports can be 450 x 450 mm slabs on mortar beds or cast concrete pads. It uses less hardstanding and leaves air beneath a timber floor, but it gives you more points to level. It suits a light shed on stable ground, not an unsupported heavy building.

Adjustable pads

Adjustable pads or risers support bearers on screw-adjusted feet. They can solve small level differences without a concrete platform, with height and load limit set by the maker. The calculator uses a 35 to 150 mm planning range and 600 mm spacing. Treat both as layout guides and choose a system with a published capacity for your shed and ground.

How the quantities are worked out

The calculator converts your shed length and width to metres and multiplies them to find the footprint. Concrete volume is footprint multiplied by 0.1 m, with a 10% allowance for waste. MOT Type 1 is footprint multiplied by 0.075 m, then converted to tonnes at about 2.1 tonnes per cubic metre, the figure implied by a standard 800 kg bulk bag's stated coverage. Following cement maker guidance for a general-purpose mix, each cubic metre of concrete takes 14 bags of 25 kg cement and 1 cubic metre of all-in ballast, about 1.75 tonnes. Bag counts round up to whole 25 kg bags and bulk bags to whole bags.

For paving, the slab count is the footprint divided by 0.6 x 0.6 m, rounded up. The 25 mm mortar bed uses sharp sand at about 1.5 tonnes per cubic metre and cement at 1 part to 4 parts sand, and the sub-base uses the MOT figure above. Grid panels are the footprint divided by 0.5 x 0.5 m, rounded up. Gravel fills the 40 mm grid depth at about 1.7 tonnes per cubic metre. Real ground and compaction can change the order, so treat the result as an estimate.

Prices change and delivery can dominate a small order, so check the product pack before ordering. The fitted concrete range is a separate benchmark from two dated UK cost surveys, not a quote for your garden.

Do not forget the finished height

The base changes how high the shed sits. The heights shown are typical amounts each base adds above the ground beside it; measure your own once the base is laid. Add the base height to the shed's own eaves and roof height before you decide where it can go. In England, the government's permitted development guidance says that if any part of an outbuilding is within 2 metres of the boundary, the total height limit is 2.5 metres. The measurement is taken from the highest ground level immediately beside the building to its highest point. A taller shed or a different planning context may need permission, so read shed planning permission before you buy.

If you are unsure how much a raised floor will affect access, door clearance or future maintenance, see how to move a shed. A few minutes spent checking the finished height is cheaper than rebuilding a base.

When to get a professional

Get a site-specific view for a heavy log cabin, garden room, made-up ground, poor drainage, retaining walls or a steep slope. A professional can assess levels, access, excavation and load paths. If the shed will be a heated office or workshop, ask the maker for the foundation detail first, then use this calculator only for quantities around that specification.

Frequently asked questions

What is the best base for a garden shed?

For a typical timber shed, a level concrete slab is the most robust option, while paving slabs, a gravel-filled plastic grid or bearers on pads can work well when the ground and shed suit them. The right choice depends on access, slope, drainage, weight and how permanent the building will be.

How thick should a concrete shed base be?

This calculator uses a 100 mm concrete slab over a 75 mm compacted MOT Type 1 sub-base for a normal garden shed. Treat that as a planning figure, not a structural design. A log cabin, workshop or garden room may need a thicker or reinforced base specified by its maker.

Should a shed base be bigger than the shed?

The calculator sizes the base to the shed footprint. That avoids a projecting ledge where rain can splash onto the lower timber. If your shed maker specifies an overhang, drainage edge or different footprint, use the maker's dimensions instead and check the finished height at the boundary.

Can I put a shed on paving slabs?

Yes, if the slabs are fully supported, stable and level. Use a properly prepared sub-base and a full mortar bed for a firm installation. Do not rely on loose slabs laid on soft soil, because movement can twist the shed and let water stand beneath it.

How long before I can build on a concrete base?

The calculator allows 28 days before building on a new concrete slab. Concrete can be walked on sooner, but it continues gaining strength while it cures. Protect the pour from rapid drying and follow the concrete or shed maker's instructions if they require a different period.